Can somebody enlighten me on the functions of
production version and some tips on its configuration?
Production Versions are used to describe the production
process to be used for planned / production order.
You can use the production versions based on:
1. Lot size qty
2. Bom explosion dates
3. Based on MRP Group
Why is it required?
Suppose you have 2/3 production lines and 2/3
alternative BOMs to produce one FG.
How system will come to know which BOM and Routing to
be used. This is done thru Prod.Version.
In production version we maintain the combination of
BOM and routing.
Also it can be designed with lot size or validity period.
Go to MM02--->MRP4 / Work scheduling view ---->
Prod.Version.
Enter the validity period and lot size.
After entering the reqd. routing no. and BOM alternative ,
carry a check.
After getting the Green signals ,Continue.
Thus you have saved the prod. version.
Mass processing TCode- C223.
Does this mean that I have to activate all the BOM�s
if in case I have 3 alternative BOM�s? if yes, then, will it these 3 BOM�s be
exploded in MRP? I�m just worried �coz I might bloat our inventory if there are
three active BOM�s.
No.First of all need not worry about the BOM explosion.
As I told you earlier which BOM and which Routing is
decided by Prod.Version.
So in MRP the active prod.version only will be
considered. Thus active BOM and active Routing will be used for MRP.
The question comes: How to deactivate the alternative
BOMs and Routing?
Two Ways:
1. You lock all other non-relevant Prod.Versions in MM02
of the FG/SFG material.(Every alternative BOM and routing forms a Prod.Version)
Thus even if there are 2/3 prod.versions System will go and check for Unlocked
prod. version and use it.
2. If you don't want to do this business of "Lock &
Unlock" just place the required version at the first place in list of
prod.versions in MRP4 view of the material.
Once system finds the first prod.version it will not spend
energy in searching other alternatives.
Also please.don't forget to maintain the selection
value of "2" in MRP 4 view for BOM selection.