Explain the procedure to create PR or PO by MRP?
p { margin-bottom: 0.21cm; }
The procedure to create PR is according to the safety stock mentioned for the material or can be triggered from a requirement. For creating a PO, you need to have the scheduling agreement in place .After the MRP is run the schedule lines are generated which is nothing but the PO.