For SAP PP module what are the cutover activities followed?
The following are some of the cut over activities that are to be followed for PP Discrete Manufacturing: Production Planning/ Master Data: In PP only master data shall be migrated to SAP; there is no master data in the first stage. The elements that are related to PP in the master data are Bill of Materials, Routing and Work Centers.
Transaction Data: As per the cut off date, ideally there should not be any work in process, all the open production orders should be closed and semi finished goods would be dismantled and should be added to Raw materials. This strategy should be followed for all production order where lead time to complete the production order is not large.
Since, the production orders are for longer duration and it is not possible to dismantle the product and add it to inventory, following can be the strategy to migrate the data to SAP It create a material master for the work in process and set the standard price as the cost incurred for that product (Work in process), create a bill of material, which will be used only for this production order including this material and other materials still to be consumed. It creates Routing for rest of the production process. Bring the work in process material into inventory as of the cut off date. It creates the production orders in SAP for the Work in process and issue materials to production order.