What is the procedure for MPS in Back ground online when it was run for a plant either ways?
p { margin-bottom: 0.21cm; }
MPS in Back ground online was run for a plant in either ways it would run MPS for a single material/plant, if it does not work it need to run a planning file and a consistency check first, transaction OMDO and MDRE respectively it require to set up two jobs to do it but it is straight forward, once it was done this set up the back ground job MPS to run and do it in NEUPL first time round and then change to NETCH after that.